Solution of waterproofing works under frequent rain showers

All works of our approved applicators has been postponed in the event of rain since June. One special case to share here:

1) Applied 2K Epoxy Moisture Barrier one day before

2) Heavy rain poured in the Morning

3) Workers clear and dry the substrate afterward

4) DELTA QA Officer carried out Moisture Reading to approve the application Delta products

5) Spray works

6) Raining again...

Probably, this is the best solution of works under frequent rain showers.

Rain pours frequently
Moisture Reading

Primer

Spray

Completion